Key scheme dates

 

Key:

ES – Environmental Stewardship including ELS, OELS, UELS, OHLS and HLS

CS – Countryside Stewardship

BPS – Basic Payment Scheme

EWGS – England Woodland Grant Scheme

 

Date

 

Scheme

 

Deadline / milestone

 

30th April

CS – Water Capital Grant 2015

Application deadline.

 

30th April

CS – Woodland Creation grant

Draft application must be submitted to Forestry Commission.

13th May

CS – Facilitation Fund

Application deadline

 

15 May 2015

BPS

 

 

Land you use to claim BPS in 2015 has to be ‘at your disposal’ on this date

31st May

CS - Woodland Creation grant

Application deadline

 

15th June

CS – multi annual

Expect CS manual to be published

Midnight on 15 June 2015

BPS

-          BPS 2015 application deadline

- Deadline for RPA to receive RLE 1 forms for entitlement transfers.

- Only the person who holds an entitlement at midnight on 15 June 2015 can use it to get paid for BPS in 2015

- Deadline for RPA to receive RLE 1 forms for land transfers (to use land for BPS 2015, the land must have been at the applicants disposal on 15 May 2015)

- Deadline for RPA to receive RLE 1 forms telling them about mapping changes (such as permanent changes to field boundaries or to tell us about permanent ineligible features that aren’t already included on your maps)

- Deadline for RPA to receive evidence to prove active farmer, young farmer or new farmer status

Midnight on 15 June 2015

ELS/HLS/ EWGS

Deadline for ES claim forms

 

Midnight on 10 July 2015

 

BPS

Deadline for late BPS applications, or late amendments, with penalty

 

Midnight on 10 July 2015

 

ELS/HLS/ EWGS

Deadline for late ES Claim forms, or late amendments, with penalty

30th June

CS – Higher Tier

Submit Expressions of Interest for higher tier applications

1st July

CS – multi annual

Application window opens for:

- Higher tier

- Mid-tier

- Capital grants including water capital grants

30th September

 

 

 

CS – multi annual

Application deadline for:

- Higher tier

- Mid-tier

- Capital grants including water capital grants

 

1st January 2016

CS – multi annual

Agreements start for

- Higher tier

- Mid-tier

- Capital grants including water capital grants

 

 

What about cross compliance?

Don’t forget that cross compliance dates apply also – click here to read our briefings, and here to see Defra's Cross Compliance Guidance for 2015.

 

What if I have land in more than one part of the UK?
If you have land in more than one part of the UK, you need to submit your application (and any supporting documents) by midnight on the deadline set by the agency that is paying you – more information can be found about cross-border claims here.